Local · News article
This morning, New York City mayor Zohran Mamdani laid out a plan to close Rikers Island by 2032, the same year that the Manhattan Borough-Based Jail (BBJ) is slated to become operational. But the scheduled completion date for the Manhattan BBJ is now in question, after nighttime construction was recently halted by a judge.
Welcome to Chinatown, Neighbors United Below Canal, community leaders, and Chinatown seniors filed a lawsuit in October against the City of New York to stop nighttime construction on the Manhattan BBJ.
The plaintiffs are worried about enduring another seven years of rumbling noise, dust, and bright lights creeping into their apartments at night. They argue that the city unlawfully approved the extended construction hours without conducting an additional environmental review.
Five days after the suit was filed, Justice Kathy King, a Manhattan Supreme Court judge, issued a Temporary Restraining Order (TRO), halting after-hours construction.
“Borderline Uninhabitable”
The Manhattan BBJ’s address is 125 White Street. As part of the BBJ program, Rikers Island will be shut down and replaced with four jails across four boroughs. Designed by HOK, the 335-foot building slated for Manhattan is expected to be the tallest jail in the world. (Ideas of Order, a local architecture firm, proposed a housing alternative for the site.)
According to the October lawsuit, in 2019, the city conducted an environmental impact assessment of the Manhattan BBJ. The assessment evaluated the effects of construction based on the assumption that work would take place on weekdays between 7:00 a.m. and 6:00 p.m. (although “normal” hours were expected to end at 3:30 p.m.) over a four-year period from 2022 to 2026.
The city is significantly behind schedule. To complete the jail by its revised 2032 completion target, the city approved extended construction hours. According to the lawsuit, beginning October 12, work was permitted from 6:00 a.m. to midnight Monday through Friday, with construction activities scheduled to end by 10:00 p.m. and from 9:00 a.m. to 5:00 p.m. on Saturdays.
Chinatown residents allege construction trucks have been delivering materials as early as 4:00 a.m. For some residents, this has been unbearable.
“I couldn’t really take it, I had to get out,” said Joseph Olisaemeka Wilson, a Chinatown resident who lived on Baxter Street up until about three weeks ago. Olisaemeka Wilson is now subletting from a friend a few blocks away in Little Italy, he told AN, to get away from the construction.
Olisaemeka Wilson described living close to the development as “borderline uninhabitable.” He emphasized that, while he was lucky enough to be able to move, others have not been so fortunate.
Some residents, specifically the senior citizens living in Chung Pak—a 13-story residential tower that provides low-income senior housing, situated right next to the construction site—have not been able to find other accommodations.
“A First Real Step”
How the Chinatown’s seniors are fairing with the construction is one of the community’s biggest concerns. The Chung Pak building is located directly next to the construction site; most of its residents are in their mid-eighties and nineties, which raises concerns about the effects of construction noise, vibrations, and dust on their health.
“No sound blanket really makes 10:00 p.m. drilling acceptable outside of a senior bedroom window,” said Allie (Alice) Luu, head of communications at Welcome to Chinatown, one of the groups that filed the lawsuit.
The community’s main issue is that the city is rushing to meet a deadline and in turn Chinatown is paying the price. Luu stressed, however, that does not mean Welcome to Chinatown does not believe Rikers should close, just that their community should not be sacrificed for it.
As of now, the city has moved to dismiss the petition and complaint, and both sides have agreed to extend the deadline for the city’s next legal filing. “The Motion to Dismiss shall be returnable on December 1, 2026,” the document states.
“This is a first real step of many, because we know that we are going up against the city with this lawsuit,” Luu told AN. “But we recognize there’s a lot of work ahead,” she said, acknowledging that the restraining order is temporary.
City Hall did not respond to a request for comment.